Guide · Planning

Planning permission for an extension in Dún Laoghaire-Rathdown

At a glance Most single-storey rear extensions in Dún Laoghaire-Rathdown don’t need planning permission. They must stay within 45 m² in total (counting every extension since 1964), leave at least 25 m² of garden and be no higher than the house. Front and side extensions, larger first floors, and homes in conservation areas or on the protected structures list need permission. Every extension must still meet the Building Regulations.

45 m²rear extensions can be exempt

25 m²garden you must keep

8 + 4 weeksdecision and appeal

DLRDún Laoghaire-Rathdown County Council

Key figures

RuleLimit
Rear extension, total floor area (exempt)45 m², including all extensions since 1 October 1964
Garden left after buildingAt least 25 m² of private open space
First floor, semi-detached or terraced (exempt)12 m²
First floor, detached (exempt)20 m²
Distance from party boundary (above ground floor)At least 2 m
Upper-floor windows facing a boundaryAt least 8 m away
HeightNo higher than the house
Section 5 declaration (is it exempt?)€80 council fee
Planning application fee, works to a house€34

When does an extension need permission?

Exempted development rules only cover the rear of the house. You need planning permission when any of these apply:

  • The extension is at the front or side (a small porch is the exception).
  • Together with earlier extensions, it goes over 45 m².
  • The first floor is over 12 m² on a semi or terrace, or 20 m² on a detached house.
  • Less than 25 m² of garden would be left.
  • The house is a protected structure, or the work would affect the character of an Architectural Conservation Area. Parts of Foxrock, Dalkey, Monkstown and the Dún Laoghaire seafront are in conservation areas.
  • The original planning grant for your estate removed exempted development rights. Check the conditions on DLR’s online planning register.

How long does a planning application take in DLR?

  1. Drawings and notices (2 to 4 weeks): scaled plans, a newspaper notice and a site notice.
  2. Public submissions (5 weeks from lodging): neighbours can comment.
  3. Council decision (8 weeks from lodging, longer if further information is requested).
  4. Appeal period (4 weeks): anyone who made a submission can appeal to An Coimisiún Pleanála.

Allow 12 to 16 weeks in total before building can start.

Exempt doesn’t mean no rules

An exempt extension must still meet the Building Regulations: structure, fire safety, ventilation and energy performance. Keep an engineer’s certificate of compliance, product certificates and photos of the build-up before it’s covered. A buyer’s solicitor will ask for them.

Questions

Does an old kitchen extension count towards the 45 m²?

Yes. Every extension built since 1 October 1964 counts, even one that had full planning permission.

Does a garage conversion count?

Converting an attached garage at the side or rear is usually exempt, but its floor area counts towards the 45 m² limit.

How do I know for certain if my extension is exempt?

Apply to Dún Laoghaire-Rathdown for a Section 5 declaration. The fee is €80 and it gives you a formal answer.

What if I build without permission when I needed it?

The council can take enforcement action. You can apply for retention, but if it’s refused you may have to remove the extension, which is far more expensive than applying first.

Sources