Planning permission · Dublin

Planning permission for extensions in Dublin

We tell you on the first visit whether your project is exempt. If it isn’t, we prepare the drawings and application and see it through, with Dún Laoghaire-Rathdown, Dublin City, South Dublin or Fingal County Council.

At a glance Since 27 July 2026, a single-storey rear extension can be exempt from planning permission up to 45 m² in total, counting earlier extensions. At least 25 m² of garden must be left, and it can’t be higher than the house. Front and side extensions, larger first floors, protected structures and most work in conservation areas need permission. A council decision takes about 8 weeks, plus 4 weeks for any appeal.

45 m²rear extensions can be exempt

8 weekscouncil decision

4 weeksappeal period

€1,500–4,000drawings and application

2026 rules

What you can usually build without permission

Usually exempt

Rear extension up to 45 m²

Single-storey, counting every extension since 1964, with 25 m² of garden left.

Check first

First-floor rear additions

Up to 12 m² above ground floor on a terraced or semi-detached house, 20 m² on a detached house, 2 m from the boundary.

Usually exempt

Rear dormers and rooflights

New under the 2026 rules, within limits, for attic conversions.

Usually exempt

Garage conversion

An attached garage converted into part of the house, counting towards the 45 m².

Notify the council

Granny flat or splitting the house

A 32–45 m² unit in the rear garden, or two homes within the house; notify the council 14 days before. See granny flats.

Needs permission

Front, side, protected, conservation

Also estates where the original permission removed exempted development rights.

Not sure? A Section 5 declaration from the council confirms in writing whether something is exempt.

When you need permission

How we handle the application

Feasibility

We check the development plan, nearby decisions and anything that could cause objections.

Week 1

Drawings and notices

Planning drawings, site notice and newspaper notice, then we lodge the application.

Weeks 2 to 6

Council decision

The council decides within 8 weeks, unless it asks for more information.

8 weeks

Appeal period, then build

4 weeks for any appeal to An Coimisiún Pleanála, then the final grant.

4 weeks

Councils

Which council handles your house

Dún Laoghaire-Rathdown

Dublin 18, Blackrock, Dalkey, Killiney, Dundrum, Goatstown, Ballinteer.

Dublin City

Dublin 2 to 9, Rathgar, Terenure, parts of Rathfarnham.

South Dublin

Knocklyon, Firhouse, Templeogue, Tallaght, Clondalkin, parts of Rathfarnham.

Fingal

Dublin 15: Blanchardstown, Castleknock, Clonsilla, and parts of Santry.

In Dún Laoghaire-Rathdown? Read our detailed DLR planning guide.

Questions

Planning questions

How much does planning permission cost?

Drawings and the application typically cost €1,500 to €4,000, plus the council’s fee and the newspaper notice. Complex or conservation-area projects cost more.

How long does planning permission take in Dublin?

Allow 12 to 16 weeks from lodging to final grant: about 8 weeks for the decision and 4 weeks for the appeal period. A request for further information adds time.

Does an exempt extension still need certificates?

Yes. Exemption is from planning only. The work must meet the Building Regulations, and you’ll want an engineer’s certificate of compliance for when you sell.

Can a neighbour object?

Yes, within 5 weeks of the application being lodged. We design to avoid the usual grounds, such as overlooking and overshadowing, and talk to neighbours early where it helps.

Exempt, or not?

Book a free consultation and get a clear answer before you spend anything on drawings.